School Building Committee update

In an effort to keep our community informed about the High School Building Project, the School Building Committee (SBC) of the Nashoba Regional School District has provided an update which you will find below. Please note that a School Building Committee Updates link can be found on the Board of Selectmen page to provide access to this and any future communications from the SBC.


On July 27, 2021, the OPM Selection Subcommittee interviewed three companies (Colliers
Project Leaders, Dore+ Whittier, and Skanska) who were chosen from the 11 applications
received to provide services as the Owner’s Project Manager for the Nashoba High School
Building Project. On July 28, 2021, the OPM Selection Subcommittee voted to select Skanska
as the OPM finalist. At the OPM Review Panel on September 13, 2021, the MSBA approved
Skanska as the OPM for our building project. This is a significant milestone within the MSBA
process, and Nashoba is extremely excited to welcome Skanska to our project team. Skanska
has successfully led a multitude of other school districts through this process, including
Minuteman Regional Vocational Technical High School. Skanska will promptly begin to assist
the District in undertaking the designer selection process to complete our project team.
Skanska’s presentation to the MSBA, including the projected timeline shown below, is also
available on the Nashoba School Building Committee website.

Click to view Projected Project Timeline

If you’re interested in learning more about how the project team will be formed, click here. If
you have any questions, please contact Joseph Gleason, chair of the Nashoba SBC at